The operator needed one partner for the whole move: measurement and verification of every rig component during disassembly at the Oklahoma refurbishment yard, a logistics plan that staged refurbishment and road transport against a strict vessel loading window, and stowage planning for a 68-package set crossing the Atlantic.
The heaviest piece weighed 90,000 lb and the longest measured 70 ft. Every stage needed special permits and crane coordination.
Field engineers verified dimensions and weights for accurate permitting and trucking assignments across all 68 assemblies.
Specialized trailers and crane assets secured at origin in Oklahoma and at the port in Houston.
68 loads coordinated to arrive in the order Houston export scheduling and the refurbishment crews required.
Multi-day loadout at WATCO Terminal Houston with stevedores and vessel crew, using dual 150-ton cranes.
Loading, stowage and securing certified by marine surveyors for the Atlantic crossing.
Continuous updates from dispatch through vessel departure.

All 68 packages delivered on time, in full, and staged for shipment aboard M/V Industrial Courage. Marine surveyors validated securing with 8 to 10 ton chains, nylon webbing and dunnage at or above industry standards.
Zero incidents during rig-down, trucking and vessel loadout despite sub-freezing temperatures, high winds and rain. The rig arrived in Salvador, Brazil after more than 20 days of ocean transit.