Soybean plant expansion: 75 oversized components from barge to site in Minnesota
Agriculture and industrial construction
·
Project cargo, heavy haul, crane services

Soybean plant expansion: 75 oversized components from barge to site in Minnesota

CHS Inc. soybean processing plant expansion requiring 75 oversized components mobilized from barge discharge at Winona, Minnesota to the construction site in Fairmont, about 180 miles away.
75
Components delivered
1.9M lb
Total weight moved
0
Cost overruns or incidents
Winona, MN to Fairmont, MN, 180 miles
Route
Crane lifting a plant vessel onto a truck at the Winona, Minnesota terminal
Crane lifting a plant vessel onto a truck at the Winona, Minnesota terminal
Route:
Winona, MN to Fairmont, MN, 180 miles

The challenge

The expansion required the safe and timely delivery of 75 plant components discharged from barge at Winona, MN and transported roughly 180 miles to the construction site in Fairmont, MN. Total weight was 1,939,359 lb, with the largest unit at 70,000 lb.

The project ran through COVID-19 driver and equipment shortages, DOT route surveys that were canceled mid-project, and lightning and high winds that interrupted barge discharge and crane operations.

What we did

Crane services

Equipment and certified operators sourced for barge discharge at Winona Terminal and for offloads at the construction site.

Specialized trucking

75 transport units dispatched: 33 standard flatbeds, 19 double drops, 17 extendable double drops, 5 six-axle step deck extendables and 1 RGN extendable, each matched to the component's dimensions and weight.

Permits and escorts

Oversize approvals coordinated with DOT and state police. When DOT canceled approved routes mid-project, surveyors were deployed the same day and alternate routes secured.

Weather disruption

Standby costs negotiated with drivers and crane operators during storms to keep the project on budget.

Real-time updates

Continuous stakeholder communication through every phase.

Results

All 75 components delivered on time with no disruption to the construction schedule, and no penalties, demurrage or excess charges across the project.

Zero safety incidents across barge discharge, crane operations and trucking, with stakeholder visibility maintained throughout the pandemic.

A complex industrial mobilization delivered on time, in the middle of a global shutdown.